The Control Of Dust And Emissions Construction Essay

This outline method statement is produced in conformity BS6187 Code of Practice for destruction along with considerations to The Best Practice Guidance to The control of dust and emanations from building and destruction.

2. Scope Of Works

This papers covers the destruction of the undermentioned edifice.

This papers covers the undermentioned affairs:

M & A ; E Services and Structural studies

Soft strip constructions of internal fixtures and adjustments

Destruction of constructions

Transporting and oppressing on/off site of suited stuffs

Installation of all brinies services

Preparation of estate roads

3. Working Hourss

DOTLAMB criterion working hours are 08.00 – 18.00 Monday – Friday. Weekend working will merely be arranged if necessary with the Client and Local Authority. DOTLAMB understands that the local authorization has limitations on site working hours ( shown below ) . DOTLAMB concludes that our standard working hours fall within the prescribed timings.

Monday – Friday 07.00 – 19.00

Sabbatums 09.00 – 12.00

Lord’s daies and Bank Holidays No Work

4. Legislation and Codes Of Practice

All work will be carried out in conformity with current statute law and criterions with peculiar respect to the followers:

The Health & A ; Safety at Work etc Act 1974

The Construction ( Health, Safety & A ; Welfare ) Regulations 1996

The Control of Asbestos at Work Regulations 2006

The Asbestos ( Licensing ) Regulations 1998

Working with Asbestos Insulation etc ( 2nd Edition ) 1987 Regulations

The Control of Lead at Work Regulations 1998

Control of Pollution Act ( Amendments ) 1989

The ( Lifting Operations & A ; Lifting Equipment ) Regulations 1998

Health and Safety at Work Regulations 1999

The Control of Substances Hazardous to Health Regulations 2002

The Construction ( Design & A ; Management ) Regulations 1994

The Management of Health & A ; Safety at Work Regulations 1999

Personal Protective Equipment at work Regulations 1992

The Construction ( Head Protection ) Regulations 1989

The Health & A ; Safety ( Safety Signs & A ; Signals ) Regulations 1996

The Noise at Works Regulations 1989

The Health & A ; Safety ( First Aid ) Regulations 1981

The Workplace ( Health, Safety & A ; Welfare ) Regulations 1992

The Reporting of Injuries, Diseases & A ; Dangerous Occurrences Regulations 1995 ( RIDDOR )

The Provision & A ; usage of Work Equipment Regulations

BS6187 Code of Practice for Demolition

BS5240 Industrial Safety Helmets

BS2092 Industrial Eye Defenders

BS5228 CP for noise control on building and open sites

5. Pre-Commencement Plants

Due to the complexness of the vetch field bowl, DOTLAMB believe it is necessary to let a lower limit of a 4-week pre-commencement period for appraising, design and blessing of plants prior to destruction plants. During this period DOTLAMB D & A ; B Contractors envisage transporting out the undermentioned work.

Correlation of bing drainage with service programs and be aftering for remotion, cresting and protection of drainage

Survey of bing statutory services, meetings with client representative and statutory suppliers

Structural studies of edifices to be demolished

Design of impermanent plants to ease destructions

Dilapidation study of environing buildings/roads

Development of traffic direction program

6. Health, Safety and public assistance installations

Temporary public assistance installations will be provided for and by DOTLAMB D & A ; B Contractors sit staff and secret agents in a location agreed with Swansea City Council and between DOTLAMB and the client ‘s representative.

DOTLAMB D & A ; B Contractors will supply a qualified first assistance representative and a suited first assistance box.

All works operators will be CITB ( Construction Industry Training Board ) , CPCS ( Construction Plant Competence Scheme ) , CTA ( Certification of Training Achievement ) , registered and will transport transcripts of their certifications on their individuals for review.

All site forces will be issued with the necessary PPE ( personal protective equipment ) and will be expected to have on it at all times on site. Particular PPE will be issued to forces as necessary.

During the initial site initiation all site forces will be made cognizant of the clients site regulations, accident coverage and site exigency processs. These will be adhered to at all times while on site.

7. Public and Employee Protection

7.1 Servicess

Servicess are known to be in the pathwaies and roads next to the fetch field site and enter the site at designated countries. All services to the constructions to be demolished are to be disconnected at or beyond the site boundary prior to the commencent of plants. DOTLAMB D & A ; B Contractors propose to pass a pre-commencement period working with the client and all statuary morticians to result all services are identified and isolated or their places marked/recorded as required.

Servicess within the site boundary that are to stay unrecorded will be assessed and protected as necessary. Carefully controlled manus excavated test cavities will be carried out as necessary to supply and verify the exact location and nature of recorded services.

7.2 Site margin

Warning notices and restricted country notices will be positioned at vantage points, solid barriers will be in topographic point to all site boundaries through the proviso of either timer billboard, solid Hera type fence or use of boundary walls.

The interior margin of the on the job country is to have a farther block and mesh billboard as necessary to tag active destruction zones or protected services. During the destruction of the constructions DOTLAMB D & A ; B Contractors will implement the direction of walkers and traffic jointly with the client, Swansea metropolis council and the local main roads bureau.

Access and emersion to the work force will be via designated paths. These will be agreed and implemented with the site supervisor. the Vetch Field site lies within the metropolis Centre of Swansea with lodging and a shopping complex nearby with route systems in topographic point. The bing route system is to be followed in conformity with the traffic direction strategy to be adopted. All works will be delivered to site via low stevedores, with no heavy works motions being carried out on bing roadways to guarantee the route surface and besides bing below land cloacas and drainage is non damaged through supplanting.

7.3 Workforce protection.

Areas of hazard beneath the destruction countries will be cordoned off and clearly segregated from 3rd parties. Barriers are to be erected complete with warning marks. All impermanent barriers and marks will be invariably checked and maintained before and during each working twenty-four hours by the site supervisor.

All countries of safety will be invariably monitored and evaluated with attending to detail being given the extreme concern at all times.

7.4 Personal Protective Equipment ( PPE )

All site forces will be issued with standard personal protective equipment. Each secret agent will hold general protection issued by the site supervisor depending on the work at manus. Safety wear will consist of the followers:

Hard chapeaus, ear and oculus guardians, rhinal protection against high volume dust and dust, cuticular protection to exposed vulnerable countries, footwear against hazard of incursion and impact and high visibleness vests/jackets.

8. Existing Construction

The Centre ( south ) Stand – concrete / steel framed building

The West Terrace – concrete / steel framed building

The North Bank – concrete / steel framed building

The East Stand – concrete / steel framed building

Underpass – belowground concrete building

9. Destruction Overview

Concrete / steel framed building

Following soft depriving and recovery works the safest destruction method for a constructions and sub-structures of this size and building is distant destruction utilizing specialist destruction excavators with fond regards such as pulverisors, rotational grapnels and pails to pulverize the construction and procedure reclaimable stuffs for remotion off site via back propping lorries. This method minimises the sum of work undertaken externally by destruction secret agents.

9.1 activity humor hazard risky potency

Dust, exhausts and noise – hazard appraisal attached

Traveling works and machinery – hazard appraisal attached

Manual managing – hazard appraisal attached

Uncontrolled prostration – hazard appraisal attached

Working at highs – hazard appraisal attached

Contact with services – hazard appraisal attached

Materials – hazard appraisal attached

Fire – hazard appraisal attached

Security – hazard appraisal attached

Mud on environing roads – hazard appraisal attached

Traffic – hazard appraisal attached

Resources – hazard appraisal attached

Contamination / pollution – hazard appraisal attached

9.2 Resources

Plant

Labor

High range and standard range 360-degree hydraulic excavators fitted with destruction fond regards.

Oppressing Plant.

Loading shovel.

Container skips.

Scaffold protection.

Mobil entree platforms.

Back shore uping lorries.

Road traveling Crane.

Site director.

Site supervisor.

Destruction secret agents.

Plant secret agents.

Lorry drivers.

Scaffold erectors.

9.3 PPE to be used

Safety Helmet Hi-Vis Clothing Ear Protection

Baseball gloves Respirators Safety Boots

Coveralls Eye Protection Dust Masks

Safety Harness

10. Methodology

10.1 General

Careful scheduling of all elements i.e. soft denudation and destruction is to be adopted with countries being handed over as they are cleared for the following operation. Sectional completion of countries will enable the plants to come on in the mode as described below.

10.2 Site constitution

Upon arrival secret agents are foremost to go to the site initiation class offered by the client. A farther initiation and tool chest talk is to be given by the site director placing specific points relevant to the approaching plants programme. After completion secret agents are to so set on suited PPE and reassign all necessary equipment to the working country. All power tools to be used are to be either 110v or cordless. A generator is to be used for 110v power.

10.3 Soft strip stuff remotion

The stuffs will be loaded straight into container skips. A 360-degree excavator may offer aid at land degree in guaranting full and unafraid tonss. The plants are to come on in a section-by-section mode through each base until complete. As the skips are filled wireless or phone contact is to be maintained between the land operative and the floor chief. Works will discontinue whilst skips are swapped or rearranged to enable uninterrupted filling. Access and emersion of the site are to be to the full supervised by the land secret agent at all times. Stifling down steps in the signifier of a manus held H2O spray system may be adopted should the demand arise. All run off H2O will be channelled to the nearest low point of the bases footmark. The changeless monitoring of dust will be carried and all necessary suppression will be implemented as determined by the site supervisor. Included in the soft strip will be the remotion of the evidences flood visible radiations these will be disconnected at the base of the construction and with usage of a route traveling Crane lowered on the pitch where a squad equipped with gas and air torches will cut the supporting construction into manageable subdivisions ready for remotion off site to a recycling installation. All stuffs are to be removed to licensed disposal points via sheeted lorries will full certification being supplied upon completion of the plants.

10.4 destruction of constructions

Once free of fixtures and fittings the constructions are to be demolished by the 360-degree excavator fitted with suited destruction fond regards. Aid is to be offered by the go toing 360- grade excavators fitted with suited fond regards. All destruction, processing, concrete and steel film editing plants are to be dampened down to move as a dust suppressant during the plants. Working from one base to the other in a systematic section-by-section mode the pulverisors will efficaciously level the roof subdivisions of each base into manageable pieces.

The ensuing demolished concreted and steel roof subdivisions will be allowed to fall onto the lower cordoned off country. As the plants progress the end point associated walls and columns are to be removed. Once the relevant subdivision of roof has been removed and has had all its structural support belongingss removed. The rear and side walls of each base are to be pushed inwards onto the floor by a 360-degree excavator this once more will be completed in a section-by-section mode. At land degree the attendant destruction elements are to be processed by the helping 360-degree excavator into their separate waste/recycle containers for remotion and processing. Materials are to be loaded straight into expecting container skips and are to be removed at periodic intervals to advance a clean, tidy and safe working environment. Separation of all crushable stuffs will be an on-going procedure with reserves created at suited points expecting the beginning of oppressing plants.

10.5 destruction of infrastructures

The subway and land floor countries of the bases are to be broken out utilizing 360-degree excavators fitted with hydraulic surfs, rending maulerss or pails. Once the slabs have been pulled up and stockpiled by the excavator the stuffs are so to be reduced in size, if necessary, utilizing 360-degree excavators fitted with concrete demolishing fond regards.

10.6 Site clearance

Site clearance will dwell of all destruction stuffs being removed, clearance and cleansing of works and material storage countries. All works to be removed on low stevedores via roadways with the exclusion of one 360-degree excavator for the installing of brinies services and readying of estate roads. A general expanse of the site by all secret agents for foreign objects and dust. Site boundaries are to stay until the installing of brinies services and back uping estate roads are constructed/prepared.

10.7 installing of brinies services

The brinies services will necessitate trenches. The 360-degree excavator will unearth these one time the surveyors have marked the countries to be excavated. Once trenches have been excavated the brinies services can be placed in to the trenches, connected and caped where required so backfilled and recorded for protection for both public/workforce and the services themselves.

10.8 readying of estate roads

The readying for estate roads will get down on the completion of the installing of brinies services and will dwell of unearthing the needed paths set by the client and marked by a squad of surveyors, routing drainage as required and routing electrical services for the installing of street lamps as required.

This method statement is to be read in concurrence with the associated hazard appraisals attached.

11. Coshh

DOTLAMB D & A ; B Conttractors will utilize the undermentioned merchandises on site

Diesel fuel

Lubrication lubricating oil

Hydraulic oil

Engine oil

All merchandises will be delivered to the vetch field site via a fuel armored combat vehicle operated by a to the full trained lorry driver equipped with relevant PPE. Diesel fuel will be straight pumped into works fuel armored combat vehicles from the armored combat vehicle. Oils will be dispensed from containers into mensurating jugs so straight into works. All supplier informations sheets will be held on site.

×